2nd of 4 from Himachal Pradesh
Allocated limit
₹7.91 Cr
Median ₹8.60 Cr
Fund utilisation
99%
₹7.84 Cr recommended · 345 works
About the median
Paid to vendors
₹6.40 Cr
81% of allocation
Below median (88%)
Works completed
186
54% of recommended
Below median (83%)
From recommendation to completion
Every work this MP recommended, by stage
- Recommended by the MP345 works
₹7.84 Cr · 99% of the ₹7.91 Cr allocated
- Sanctioned by the district343 works
99% sanctioned · took 6.4 months on average (due within 45 days)
- Completed186 works
₹3.42 Cr final cost · 20.2 months from recommendation on average
2 works are still awaiting sanction, 2 of them for more than 45 days.
In plain words
What the numbers say
- Recommended 345 works worth ₹7.84 Cr, a fund utilisation of 99%, higher than 60% of 17th Lok Sabha MPs.
- The district has sanctioned 343 of them, taking 6.4 months on average.
- ₹6.40 Cr has been paid to vendors, 81% of the allocation.
- 186 works are complete, typically 20.2 months after recommendation. 101 works have geo-tagged photos on eSAKSHI.
- The largest share of funds went to Roads & bridges.
- Payments went to 117 vendors. The largest received 9.6%.
- Citizens rated completed works 5.0 / 5 on average (1 rated works).
How the score is made
MP score 68/100: finishing works counts most
- Works completed 30%54Completed ÷ recommended works.
- Spending efficiency 20%53Value of completed works ÷ money paid out. Money paid without works finished scores low.
- Fund utilisation 15%99Value of works recommended ÷ allocated limit (MoSPI’s measure).
- Proof of work 15%54Share of completed works with photos or documents uploaded on eSAKSHI.
- Funds spent 10%81Paid to vendors ÷ allocated limit.
- Vendor diversity 10%100How spread out payments are: full marks when no vendor gets over 20% of the money, none when one vendor gets everything.
i
Members of Parliament (MPs) do not have direct, operational control over the specific vendors selected for government public works. However, they exert significant indirect influence by shaping procurement frameworks, passing supplier diversity laws, and conducting oversight.
Largest vendor: BDO DHARAMSHALA MPLADS, 9.6% of payments across 117 vendors.
District sanction speed
76/100 · sanction is the district authority’s job, so this doesn’t change the MP’s rank
- Sanction speed 100%76Average days to sanction (full marks within the 45-day guideline, none at a year), and the share of works not overdue.
Activity over time
Recommendations, payments and completions by month
Sectors
Value of works by category
Who got paid
Top vendors by payments received
Implementing district authorities
The districts that sanction and execute this MP’s works
Works
346 works · the 60 most recent are listed here, all of them in the explorer · tap “Photos” to see geo-tagged photos from eSAKSHI
C/o Ambulance road from Satish kumar house to near nalla, ward no. , G.P. Nagarvan
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Kangra· #86581
₹1.0 L Completed 30 Sept 2026Rec. 22 Jan 2024Paid ₹1.0 LComp. Pucca path from Pulli to Jagat Ram house, G.P. Kathog
Roads & bridgesConstruction of footpaths and pedestrian ways· Kangra· #86737
₹1.0 L Completed 26 Sept 2026Rec. 22 Jan 2024Paid ₹1.0 Lcomp. of Under Construction Link road from main road to Darad Chowki (Harijan Basti) village Gambhir Lahar, ward no. 04, G.P. Tihri
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Kangra· #106738
₹2.5 L Completed 23 Sept 2026Rec. 20 Feb 2024Paid ₹2.5 LC/o Protection wall in Irrigation Kuhal, ward no. 05, G.P. Dadamb
Irrigation, flood & environmentConstruction of public irrigation facilities· Kangra· #119019
₹99,756 Completed 14 Sept 2026Rec. 2 Mar 2024Paid ₹99,756C/o path and protection wall near the house of Sudarshan Kumar S/o Bhikha Ram, ward no. 01, G.P. kareri
Roads & bridgesConstruction of footpaths and pedestrian ways· Kangra· #110502
₹2.0 L Completed 13 Sept 2026Rec. 22 Feb 2024Paid ₹2.0 LBeautification/ tile work of Shamshan ghat near Chander Bagha Khad, ward no. 02, G.P. Gharoh
Community buildings & public spacesCrematoriums / Energy efficient crematoriums or structures on burial / cremation ground· Kangra· #110500
₹2.5 L Completed 11 Sept 2026Rec. 22 Feb 2024Paid ₹2.5 LDevelopment and beautification of war memorial at Dharamshala
Community buildings & public spacesDevelopment of public parks· Kangra· #107624
₹20.0 L Completed 7 Sept 2026Rec. 20 Feb 2024Paid ₹20.0 LDevelopment of play ground at 2nd Indian Reserve Battalion Sakoh, Distt. Kangra, H.P.
Sports & fitnessDevelopment of playground· Kangra· #107675
₹3.0 L Completed 7 Sept 2026Rec. 20 Feb 2024Paid ₹3.0 LDevelopment of war memorial at 2nd Indian Reserve Battalion Sakoh, Distt. Kangra, H.P.
Community buildings & public spacesDevelopment of public parks· Kangra· #107679
₹2.0 L Completed 7 Sept 2026Rec. 20 Feb 2024Paid ₹2.0 LC/o Shed in Moksh Dham Balu, ward no. 02, G.P. Danoa
Community buildings & public spacesConstruction of common work sheds / common covered sitting area· Kangra· #107826
₹1.4 L Completed 5 Sept 2026Rec. 22 Feb 2024Paid ₹1.4 LC/o path with interlocking tiles from house of Omdatth to Harizan Sarayi, ward no. 03, G.P. Kasba kotla
Roads & bridgesConstruction of footpaths and pedestrian ways· Kangra· #109781
₹2.5 L Completed 5 Sept 2026Rec. 20 Feb 2024Paid ₹2.5 LC/o Jeepable road along with protection wall from Shiv Temple to the house of Madan lal etc., village bogta, G.P. Kand Kardiyana
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Kangra· #110703
₹2.8 L Completed 3 Sept 2026Rec. 22 Feb 2024Paid ₹2.8 LC/o pucca path along with protection wall near Hans Raj, Pyare lal singh land, ward no. 04, G.P. Barwala
Roads & bridgesConstruction of footpaths and pedestrian ways· Kangra· #75735
₹1.0 L Completed 2 Sept 2026Rec. 5 Jan 2024Paid ₹1.0 LC/o Pucca path with protection wall near to the house of Kuldeep kumar, ward no. 04, G.P. Barwala
Roads & bridgesConstruction of footpaths and pedestrian ways· Kangra· #111715
₹1.0 L Completed 2 Sept 2026Rec. 22 Feb 2024Paid ₹1.0 LC/o pucca path with drain from cowshed of Maan chand towards Deshraj's cowshed, ward no. 04, G.P. Barwala
Roads & bridgesConstruction of footpaths and pedestrian ways· Kangra· #111719
₹85,311 Completed 2 Sept 2026Rec. 22 Feb 2024Paid ₹85,311
17th Lok Sabha MPs from Himachal Pradesh
Ranked by MP score
| # | MP | Utilisation | Spent | Completed | Score |
|---|---|---|---|---|---|
| 1 | Anurag Singh Thakur · Hamirpur | 100% | 91% | 457 | 79 |
| 2 | Kishan Kapoor · Kangra | 99% | 81% | 186 | 68 |
| 3 | Smt Pratibha Singh · Mandi | 94% | 71% | 168 | 67 |
| 4 | Suresh Kumar Kashyap · Shimla | 88% | 82% | 151 | 57 |
Source: MoSPI eSAKSHI (eSAKSHI API (mplads.mospi.gov.in)). Fund utilisation = works recommended ÷ allocated limit (MoSPI’s definition); spent = vendor payments ÷ allocated limit; completion = completed ÷ recommended works. The MP score weighs completion, spending efficiency, utilisation, proof of work, spending and vendor diversity. How it’s calculated.