Most funds not yet used
Works recommended for only 14% of the allocated limit.
Allocated limit
₹14.70 Cr
Median ₹14.70 Cr
Fund utilisation
14%
₹2.02 Cr recommended · 16 works
Below median (76%)
Paid to vendors
₹50.8 L
3.5% of allocation
Below median (37%)
Works completed
1
6.3% of recommended
Below median (28%)
From recommendation to completion
Every work this MP recommended, by stage
- Recommended by the MP16 works
₹2.02 Cr · 14% of the ₹14.70 Cr allocated
- Sanctioned by the district10 works
63% sanctioned · took 4.4 months on average (due within 45 days)
- Completed1 works
₹3.0 L final cost · 4.6 months from recommendation on average
6 works are still awaiting sanction, 3 of them for more than 45 days.
In plain words
What the numbers say
- Recommended 16 works worth ₹2.02 Cr, a fund utilisation of 14%, higher than 1.8% of 18th Lok Sabha MPs.
- The district has sanctioned 10 of them, taking 4.4 months on average.
- ₹50.8 L has been paid to vendors, 3.5% of the allocation.
- 1 works are complete, typically 4.6 months after recommendation. 1 works have geo-tagged photos on eSAKSHI.
- The largest share of funds went to Health.
- Payments went to 7 vendors. The largest received 59%.
- No citizen ratings have been reported for completed works.
How the score is made
MP score 14/100: finishing works counts most
- Works completed 30%6Completed ÷ recommended works.
- Spending efficiency 20%6Value of completed works ÷ money paid out. Money paid without works finished scores low.
- Fund utilisation 15%14Value of works recommended ÷ allocated limit (MoSPI’s measure).
- Proof of work 15%20Share of completed works with photos or documents uploaded on eSAKSHI.
- Funds spent 10%3Paid to vendors ÷ allocated limit.
- Vendor diversity 10%52How spread out payments are: full marks when no vendor gets over 20% of the money, none when one vendor gets everything.
i
Members of Parliament (MPs) do not have direct, operational control over the specific vendors selected for government public works. However, they exert significant indirect influence by shaping procurement frameworks, passing supplier diversity laws, and conducting oversight.
Largest vendor: DALBEER SINGH, 59% of payments across 7 vendors.
District sanction speed
77/100 · sanction is the district authority’s job, so this doesn’t change the MP’s rank
- Sanction speed 100%77Average days to sanction (full marks within the 45-day guideline, none at a year), and the share of works not overdue.
Activity over time
Recommendations, payments and completions by month
Sectors
Value of works by category
Who got paid
Top vendors by payments received
Implementing district authorities
The districts that sanction and execute this MP’s works
Works
16 works · tap “Photos” to see geo-tagged photos from eSAKSHI
For the construction of a Panchayat building in Village Parkandi, Block Ukhimath, District Rudraprayag
Community buildings & public spacesConstruction of community centers and community halls· Rudraprayag· #321126
₹22.3 L Awaiting sanction · 23 daysRec. 9 Oct 2026Electric connection at the ancient temple located in Village Churegaon, Block Kaljikhal, District Pauri.
Electricity & lightingLighting of public spaces· Pauri Garhwal· #321131
₹2.0 L Awaiting sanction · 23 daysRec. 9 Oct 2026For providing a Basic Life Support (BLS) ambulance to the District Hospital, Pauri.
HealthPurchase of ambulances (Four, Three and Two wheelers)· Pauri Garhwal· #321144
₹28.0 L Awaiting sanction · 23 daysRec. 9 Oct 2026For the construction work of the three storey CSD canteen building in District Pauri
Community buildings & public spacesConstruction of community centers and community halls· Pauri Garhwal· #313264
₹18.0 L Awaiting sanction · 54 daysRec. 8 Sep 2026the construction of a cement concrete (CC) road from the main road to Chaubattakhal Tok in Village Panchayat Beena Malli, located in Pauri district.
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Pauri Garhwal· #279749
₹3.5 L Physical Inspection · 14 Aug 2026Rec. 6 May 2026Paid ₹3.5 LFor the establishment of a Hemodialysis Unit at District Hospital Gopeshwar, Chamoli
HealthPurchase of hospital equipment· Chamoli· #285342
₹50.0 L Sanctioned · 29 Jul 2026Rec. 13 Jun 2026Construction of a tin-shed classroom
Education & librariesConstruction of rooms and halls in school and colleges· Nainital· #278676
₹2.5 L Sanctioned · 30 Jun 2026Rec. 20 Apr 2026For the remaining electrification in Gram Panchayat Chopra Bhalon, under Ramnagar Assembly, Nainital District.
Electricity & lightingImprovement of electricity distribution infrastructure· Nainital· #278686
₹2.0 L Vendor Identification · 30 Jun 2026Rec. 20 Apr 2026Paid ₹2.0 LInstallation of 02 solar water motors and other construction works at Dhantakarna Dham (Ghandiyal Kanda Quilli) in Narendra Nagar of District Tehri Garhwal.
Drinking waterInstalling community drinking water plants· Tehri Garhwal· #195838
₹6.0 L Work partially Completed · 29 Jun 2026Rec. 1 May 2025Paid ₹2.8 LFor construction of interlock tiles and road on the footpath at Maa Chandrabadni Temple in Devprayag development block of Tehri Garhwal district.
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Tehri Garhwal· #247595
₹10.0 L Physical Inspection · 19 Jun 2026Rec. 11 Nov 2025Paid ₹10.0 LFor construction of interlock tiles and road on the footpath at Maa Chandrabadni Temple in Devprayag development block of Tehri Garhwal district.
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Tehri Garhwal· #270311
₹20.0 L Physical Inspection · 19 Jun 2026Rec. 24 Feb 2026Paid ₹19.9 LReconstruction work of roads damaged due to heavy rainfall and cloudburst in Gram sabha Jogari, Block Khirsu, Tehsil Srinagar, District Pauri Garhwa
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Pauri Garhwal· #266806
₹2.5 L Physical Inspection · 19 May 2026Rec. 6 Feb 2026Paid ₹2.5 Lthe reconstruction of roads damaged due to heavy rainfall and cloudburst in Village Sainji, Block Pabo, District Pauri Garhwal
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Pauri Garhwal· #266805
₹10.0 L Awaiting sanction · 268 daysRec. 6 Feb 2026Construction of Road from Kamdai Motor Road to Suyalon Ki Basti (Khwal) Block Bironkhal in Pauri Garhwal
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Pauri Garhwal· #221553
₹3.0 L Completed 11 Dec 2025Rec. 23 Jul 2025Paid ₹3.0 LExtension of Martyrs Memorial Centre
Community buildings & public spacesConstruction of additional rooms and halls in the existing public and community building· Chamoli· #242341
₹10.0 L Awaiting sanction · 382 daysRec. 15 Oct 2025
18th Lok Sabha MPs from Uttarakhand
Ranked by MP score
| # | MP | Utilisation | Spent | Completed | Score |
|---|---|---|---|---|---|
| 1 | Ajay Bhatt · Nainital Udham Singh Nag. | 87% | 39% | 117 | 55 |
| 2 | Mala Rajya Laxmi Shah · Tehri Garhwal | 68% | 44% | 84 | 45 |
| 3 | Trivendra Singh Rawat · Hardwar | 32% | 7.1% | 3 | 29 |
| 4 | Ajay Tamta · Almora | 22% | 4.6% | 3 | 28 |
| 5 | Anil Baluni · Garhwal | 14% | 3.5% | 1 | 14 |
Source: MoSPI eSAKSHI (eSAKSHI API (mplads.mospi.gov.in)). Fund utilisation = works recommended ÷ allocated limit (MoSPI’s definition); spent = vendor payments ÷ allocated limit; completion = completed ÷ recommended works. The MP score weighs completion, spending efficiency, utilisation, proof of work, spending and vendor diversity. How it’s calculated.