State profile
Puducherry
2 MPs: 1 in the Lok Sabha and 1 in the Rajya Sabha. Median MP score 56 out of 100.
Allocated
₹50.23 Cr
2 MPs
Fund utilisation
88%
₹44.38 Cr recommended · 185 works
Sanctioned
52%
81 works waiting over 45 days
Paid to vendors
₹15.74 Cr
31% of allocation
Works completed
45
24% of recommended works
Follow the money
Bar length relative to the largest stage
- Allocated limit₹50.23 Cr
- Recommended by MPs₹44.38 Cr
88% fund utilisation · 185 works
- Paid to vendors₹15.74 Cr
31% of allocation · 129 payments
- Value of completed works₹9.69 Cr
45 works finished
Top sectors
Value of works recommended in Puducherry
MPs from Puducherry
Ranked by MP score. How it’s scored
| # | MP | House | Utilisation | Spent | Completion | Score |
|---|---|---|---|---|---|---|
| 1 | Shri S. SelvaganabathyRajya Sabha | Rajya Sabha | 98% | 39% | 29% | 63 |
| 2 | Vaithilingam VePuducherry | Lok Sabha | 74% | 20% | 17% | 49 |
Implementing agencies
District authorities with the most works recommended
| Agency | Works | Awaiting sanction | Completed | Avg time |
|---|---|---|---|---|
| Puducherry | 176 | 80 (72 late) | 44 (25%) | 7.1 months |
| Kancheepuram | 6 | 6 (6 late) | 0 (0%) | — |
| Tiruvannamalai | 2 | 2 (2 late) | 1 (50%) | — |
| Mayiladuthurai | 1 | 1 (1 late) | 0 (0%) | — |
Worth asking about
Each flag states the rule that triggered it. It prompts a question; it is not a finding of wrongdoing.
- Vaithilingam VeLok Sabha
Works waiting for sanction
45 recommended works are still awaiting sanction more than 45 days later. Sanction is the district authority’s responsibility.