State profile
Mizoram
2 MPs: 1 in the Lok Sabha and 1 in the Rajya Sabha. Median MP score 40 out of 100.
Allocated
₹17.15 Cr
2 MPs
Fund utilisation
84%
₹14.48 Cr recommended · 289 works
Sanctioned
69%
76 works waiting over 45 days
Paid to vendors
₹10.53 Cr
61% of allocation
Works completed
134
46% of recommended works
Follow the money
Bar length relative to the largest stage
- Allocated limit₹17.15 Cr
- Recommended by MPs₹14.48 Cr
84% fund utilisation · 289 works
- Paid to vendors₹10.53 Cr
61% of allocation · 341 payments
- Value of completed works₹7.04 Cr
134 works finished
Top sectors
Value of works recommended in Mizoram
MPs from Mizoram
Ranked by MP score. How it’s scored
| # | MP | House | Utilisation | Spent | Completion | Score |
|---|---|---|---|---|---|---|
| 1 | Richard VanlalhmangaihaMizoram | Lok Sabha | 88% | 68% | 49% | 61 |
| 2 | Shri Khiangte LaltluangkimaRajya Sabha | Rajya Sabha | 61% | 21% | 0% | 19 |
Implementing agencies
District authorities with the most works recommended
| Agency | Works | Awaiting sanction | Completed | Avg time |
|---|---|---|---|---|
| Aizawl | 85 | 21 (18 late) | 33 (39%) | 7.7 months |
| Mamit | 45 | 10 (9 late) | 34 (76%) | 11.3 months |
| Lunglei | 27 | 9 (9 late) | 17 (63%) | 10.2 months |
| Kolasib | 25 | 12 (11 late) | 13 (52%) | 13.1 months |
| Siaha | 22 | 0 | 19 (86%) | 15.8 months |
| Serchhip | 20 | 14 (12 late) | 6 (30%) | 8.8 months |
| Champhai | 19 | 8 (7 late) | 8 (42%) | 15.4 months |
| Saitual | 15 | 9 (8 late) | 3 (20%) | 5.1 months |
| Hnahthial | 15 | 2 | 0 (0%) | — |
| Khawzawl | 9 | 3 (2 late) | 1 (11%) | 7.3 months |
Worth asking about
Each flag states the rule that triggered it. It prompts a question; it is not a finding of wrongdoing.
No MP from Mizoram meets any of the attention rules.