26th of 48 from Maharashtra
Allocated limit
₹14.70 Cr
Median ₹14.70 Cr
Fund utilisation
60%
₹8.79 Cr recommended · 82 works
Below median (76%)
Paid to vendors
₹2.55 Cr
17% of allocation
Below median (37%)
Works completed
13
16% of recommended
Below median (28%)
From recommendation to completion
Every work this MP recommended, by stage
- Recommended by the MP82 works
₹8.79 Cr · 60% of the ₹14.70 Cr allocated
- Sanctioned by the district79 works
96% sanctioned · took 2.9 months on average (due within 45 days)
- Completed13 works
₹1.29 Cr final cost · 12.8 months from recommendation on average
3 works are still awaiting sanction, 3 of them for more than 45 days.
In plain words
What the numbers say
- Recommended 82 works worth ₹8.79 Cr, a fund utilisation of 60%, higher than 23% of 18th Lok Sabha MPs.
- The district has sanctioned 79 of them, taking 2.9 months on average.
- ₹2.55 Cr has been paid to vendors, 17% of the allocation.
- 13 works are complete, typically 12.8 months after recommendation. 13 works have geo-tagged photos on eSAKSHI.
- The largest share of funds went to Community buildings & public spaces.
- Payments went to 23 vendors. The largest received 7.8%.
- No citizen ratings have been reported for completed works.
How the score is made
MP score 51/100: finishing works counts most
- Works completed 30%16Completed ÷ recommended works.
- Spending efficiency 20%51Value of completed works ÷ money paid out. Money paid without works finished scores low.
- Fund utilisation 15%60Value of works recommended ÷ allocated limit (MoSPI’s measure).
- Proof of work 15%100Share of completed works with photos or documents uploaded on eSAKSHI.
- Funds spent 10%17Paid to vendors ÷ allocated limit.
- Vendor diversity 10%100How spread out payments are: full marks when no vendor gets over 20% of the money, none when one vendor gets everything.
i
Members of Parliament (MPs) do not have direct, operational control over the specific vendors selected for government public works. However, they exert significant indirect influence by shaping procurement frameworks, passing supplier diversity laws, and conducting oversight.
Largest vendor: GANESH MAJUR SAHAKARI SANSTHALTD LINGNOOR, 7.8% of payments across 23 vendors.
District sanction speed
92/100 · sanction is the district authority’s job, so this doesn’t change the MP’s rank
- Sanction speed 100%92Average days to sanction (full marks within the 45-day guideline, none at a year), and the share of works not overdue.
Activity over time
Recommendations, payments and completions by month
Sectors
Value of works by category
Who got paid
Top vendors by payments received
Implementing district authorities
The districts that sanction and execute this MP’s works
Works
82 works · the 60 most recent are listed here, all of them in the explorer · tap “Photos” to see geo-tagged photos from eSAKSHI
Construction of buildings for community cultural activities on Grampanchayat Property No.5540
Community buildings & public spacesConstruction of buildings for community cultural activities· Sangli· #174574
₹9.5 L Completed 29 Oct 2026Rec. 8 Feb 2025Paid ₹9.5 LConstruction of buildings for community cultural activities at Grampanchayat Nimbawade on Property No 09
Community buildings & public spacesConstruction of buildings for community cultural activities· Sangli· #226544
₹10.0 L Completed 19 Oct 2026Rec. 14 Aug 2025Paid ₹10.0 Lconstruction of library on property no. 5751 at Kundal.
Education & librariesConstruction of public libraries and reading rooms· Sangli· #277259
₹25.0 L Sanctioned · 7 Aug 2026Rec. 2 Apr 2026construction of building for multi-gym on property no. 297 1 at Ankalkhop
Sports & fitnessConstruction of buildings for multi-gym· Sangli· #277261
₹12.4 L Sanctioned · 7 Aug 2026Rec. 2 Apr 2026Construction of internal roads at Kognoli
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Sangli· #252801
₹10.0 L Sanctioned · 16 Apr 2026Rec. 26 Dec 2025Construction of road from talewadi road khatal vasti to karagani kalewadi road
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Sangli· #189856
₹10.0 L Completed 7 Apr 2026Rec. 8 Apr 2025Paid ₹10.0 LImprovement of road from hatti mala to royal hill station at jat umrani road jat.
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Sangli· #277262
₹20.0 L Awaiting sanction · 213 daysRec. 2 Apr 2026Construction of wall compound to Grampanchayat Property No.1252
Community buildings & public spacesConstruction of boundary walls of existing public and community buildings· Sangli· #179015
₹10.0 L Completed 27 Mar 2026Rec. 4 Mar 2025Paid ₹10.0 LConstruction of buildings for community cultural activities on Grampanchayat Property No.180
Community buildings & public spacesConstruction of buildings for community cultural activities· Sangli· #179018
₹9.9 L Completed 27 Mar 2026Rec. 4 Mar 2025Paid ₹9.9 LConstruction of buildings for community cultural activities on Grampanchayat Property No.1417
Community buildings & public spacesConstruction of buildings for community cultural activities· Sangli· #174567
₹10.0 L Completed 24 Mar 2026Rec. 8 Feb 2025Paid ₹10.0 LConstruction of buildings for community cultural activities on Grampanchayat Property No.2
Community buildings & public spacesConstruction of buildings for community cultural activities· Sangli· #174568
₹10.0 L Completed 24 Mar 2026Rec. 8 Feb 2025Paid ₹10.0 LConstruction of buildings for community cultural activities on Grampanchayat Property No.945 A
Community buildings & public spacesConstruction of buildings for community cultural activities· Sangli· #174569
₹10.0 L Completed 24 Mar 2026Rec. 8 Feb 2025Paid ₹10.0 LConstruction of buildings for community cultural activities on Grampanchayat Property No.269
Community buildings & public spacesConstruction of buildings for community cultural activities· Sangli· #174565
₹10.0 L Completed 23 Mar 2026Rec. 8 Feb 2025Paid ₹10.0 LConstruction of road from Dr Gore house to Gore road
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Sangli· #174575
₹10.0 L Completed 20 Mar 2026Rec. 8 Feb 2025Paid ₹10.0 LConstruction of road from waghmode vasti to kamat boundary
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Sangli· #189855
₹9.9 L Completed 8 Jan 2026Rec. 8 Apr 2025Paid ₹9.9 L
18th Lok Sabha MPs from Maharashtra
Ranked by MP score
| # | MP | Utilisation | Spent | Completed | Score |
|---|---|---|---|---|---|
| 1 | Smita Uday Wagh · Jalgaon | 11% | 9.5% | 9 | 74 |
| 2 | Adv Gowaal Kagada Padavi · Nandurbar | 60% | 22% | 191 | 72 |
| 3 | Chhatrapati Shahu Shahaji · Kolhapur | 100% | 30% | 37 | 67 |
| 4 | Bajrang Manohar Sonwane · Beed | 60% | 26% | 34 | 62 |
| 5 | Nitin Jairam Gadkari · Nagpur | 92% | 29% | 19 | 59 |
| 6 | Bachhav Shobha Dinesh · Dhule | 70% | 14% | 19 | 59 |
| 7 | Ravindra Vasantrao Chavan · Nanded | 85% | 39% | 34 | 58 |
| 8 | Murlidhar Mohol · Pune | 100% | 13% | 12 | 58 |
| 9 | Bhumare Sandipanrao Asaram · Aurangabad | 87% | 37% | 29 | 57 |
| 10 | Anup Sanjay Dhotre · Akola | 67% | 42% | 41 | 57 |
| 11 | Aashtikar Patil Nagesh Bapurao · Hingoli | 73% | 38% | 38 | 57 |
| 12 | Sanjay Haribhau Jadhav · Parbhani | 55% | 30% | 28 | 57 |
Source: MoSPI eSAKSHI (eSAKSHI API (mplads.mospi.gov.in)). Fund utilisation = works recommended ÷ allocated limit (MoSPI’s definition); spent = vendor payments ÷ allocated limit; completion = completed ÷ recommended works. The MP score weighs completion, spending efficiency, utilisation, proof of work, spending and vendor diversity. How it’s calculated.