Allocated limit
₹14.70 Cr
Median ₹14.70 Cr
Fund utilisation
76%
₹11.18 Cr recommended · 71 works
About the median
Paid to vendors
₹6.66 Cr
45% of allocation
Above median (37%)
Works completed
18
25% of recommended
Below median (28%)
From recommendation to completion
Every work this MP recommended, by stage
- Recommended by the MP71 works
₹11.18 Cr · 76% of the ₹14.70 Cr allocated
- Sanctioned by the district54 works
76% sanctioned · took 4.4 months on average (due within 45 days)
- Completed18 works
₹2.58 Cr final cost · 8.2 months from recommendation on average
17 works are still awaiting sanction, 16 of them for more than 45 days.
In plain words
What the numbers say
- Recommended 71 works worth ₹11.18 Cr, a fund utilisation of 76%, higher than 50% of 18th Lok Sabha MPs.
- The district has sanctioned 54 of them, taking 4.4 months on average.
- ₹6.66 Cr has been paid to vendors, 45% of the allocation.
- 18 works are complete, typically 8.2 months after recommendation. 18 works have geo-tagged photos on eSAKSHI.
- The largest share of funds went to Community buildings & public spaces.
- Payments went to 28 vendors. The largest received 15%.
- No citizen ratings have been reported for completed works.
How the score is made
MP score 56/100: finishing works counts most
- Works completed 30%25Completed ÷ recommended works.
- Spending efficiency 20%39Value of completed works ÷ money paid out. Money paid without works finished scores low.
- Fund utilisation 15%76Value of works recommended ÷ allocated limit (MoSPI’s measure).
- Proof of work 15%100Share of completed works with photos or documents uploaded on eSAKSHI.
- Funds spent 10%45Paid to vendors ÷ allocated limit.
- Vendor diversity 10%100How spread out payments are: full marks when no vendor gets over 20% of the money, none when one vendor gets everything.
i
Members of Parliament (MPs) do not have direct, operational control over the specific vendors selected for government public works. However, they exert significant indirect influence by shaping procurement frameworks, passing supplier diversity laws, and conducting oversight.
Largest vendor: Abhishek Prakash Jain, 15% of payments across 28 vendors.
District sanction speed
75/100 · sanction is the district authority’s job, so this doesn’t change the MP’s rank
- Sanction speed 100%75Average days to sanction (full marks within the 45-day guideline, none at a year), and the share of works not overdue.
Activity over time
Recommendations, payments and completions by month
Sectors
Value of works by category
Who got paid
Top vendors by payments received
Implementing district authorities
The districts that sanction and execute this MP’s works
Works
71 works · the 60 most recent are listed here, all of them in the explorer · tap “Photos” to see geo-tagged photos from eSAKSHI
Construction of a community hall at Mauje Shringartali, Taluka Guhagar, District Ratnagiri
Community buildings & public spacesConstruction of community centers and community halls· Ratnagiri· #323999
₹25.0 L Awaiting sanction · 10 daysRec. 22 Oct 2026Construction of a social hall at Surai Bouddhwadi, Taluka Mhasala, Dist- Raigad (SC)
Community buildings & public spacesConstruction of community centers and community halls· Raigad· #268172
₹15.0 L Work partially Completed · 11 Sept 2026Rec. 16 Feb 2026Paid ₹7.5 LConstruction of a community hall at Gherasurgad, Gram Panchayat Khamb, Taluka Roha, Dist-Raigad
Community buildings & public spacesConstruction of community centers and community halls· Raigad· #310965
₹10.0 L Awaiting sanction · 53 daysRec. 9 Sep 2026Construction of a community hall at Poladpur Tambadbhuvan, Taluka Poladpur, Dist-Raigad
Community buildings & public spacesConstruction of community centers and community halls· Raigad· #310972
₹30.0 L Awaiting sanction · 53 daysRec. 9 Sep 2026Construction of a community hall at Ranavali Math, Taluka Shrivardhan, Dist-Raigad
Community buildings & public spacesConstruction of community centers and community halls· Raigad· #310975
₹10.0 L Awaiting sanction · 53 daysRec. 9 Sep 2026Construction of a community hall at Sakhorone (Varchi Aali), Taluka Shrivardhan, Dist-Raigad
Community buildings & public spacesConstruction of community centers and community halls· Raigad· #310976
₹10.0 L Awaiting sanction · 53 daysRec. 9 Sep 2026Construction of a community hall at Kurvade, Taluka Shrivardhan, Dist-Raigad
Community buildings & public spacesConstruction of community centers and community halls· Raigad· #313707
₹15.0 L Awaiting sanction · 53 daysRec. 9 Sep 2026Construction of a community hall at Dalviwadi, Bagmandla, Taluka Shrivardhan, Dist-Raigad
Community buildings & public spacesConstruction of community centers and community halls· Raigad· #313708
₹10.0 L Awaiting sanction · 53 daysRec. 9 Sep 2026Construction of a community hall at Gram Panchayat Wakarul, Taluka Pen, Dist-Raigad
Community buildings & public spacesConstruction of community centers and community halls· Raigad· #313709
₹25.0 L Awaiting sanction · 53 daysRec. 9 Sep 2026Construction of a social hall at Mouje Nilgun Adivasiwadi, Gram Panchayat Degaon, Taluka Mangaon. (S.T)
Community buildings & public spacesConstruction of community centers and community halls· Raigad· #295799
₹7.5 L Work partially Completed · 8 Sept 2026Rec. 16 Jul 2026Paid ₹3.5 LConstruction of a social hall at Degaon Adivasiwadi, Gram Panchayat Degaon, Taluka Mangaon. (S.T)
Community buildings & public spacesConstruction of community centers and community halls· Raigad· #295800
₹7.5 L Work partially Completed · 8 Sept 2026Rec. 16 Jul 2026Paid ₹3.5 LConstruction of a community hall at Vaijanath, Taluka Roha, Dist-Raigad
Community buildings & public spacesConstruction of community centers and community halls· Raigad· #310964
₹10.0 L Awaiting sanction · 55 daysRec. 7 Sep 2026Construction of a social hall at Potner Adivasiwadi Taluka Mangaon, Dist-Raigad (S.T.)
Community buildings & public spacesConstruction of community centers and community halls· Raigad· #268171
₹6.0 L Physical Inspection · 31 Jul 2026Rec. 16 Feb 2026Paid ₹6.0 LConstruction of a SabhaMandap at Gram Panchayat Gangavali Bouddhawadi, Tal.Mangaon (SC)
Community buildings & public spacesConstruction of community centers and community halls· Raigad· #295798
₹10.0 L Work partially Completed · 31 Jul 2026Rec. 16 Jul 2026Paid ₹5.0 LConstruction of Social Hall at Bhuvneshwar, Taluka Roha, Dist- Raigad
Community buildings & public spacesConstruction of community centers and community halls· Raigad· #243661
₹15.0 L Work partially Completed · 22 Jul 2026Rec. 27 Oct 2025Paid ₹7.5 L
18th Lok Sabha MPs from Maharashtra
Ranked by MP score
| # | MP | Utilisation | Spent | Completed | Score |
|---|---|---|---|---|---|
| 1 | Smita Uday Wagh · Jalgaon | 11% | 9.5% | 9 | 74 |
| 2 | Adv Gowaal Kagada Padavi · Nandurbar | 60% | 22% | 191 | 72 |
| 3 | Chhatrapati Shahu Shahaji · Kolhapur | 100% | 30% | 37 | 67 |
| 4 | Bajrang Manohar Sonwane · Beed | 60% | 26% | 34 | 62 |
| 5 | Nitin Jairam Gadkari · Nagpur | 92% | 29% | 19 | 59 |
| 6 | Bachhav Shobha Dinesh · Dhule | 70% | 14% | 19 | 59 |
| 7 | Ravindra Vasantrao Chavan · Nanded | 85% | 39% | 34 | 58 |
| 8 | Murlidhar Mohol · Pune | 100% | 13% | 12 | 58 |
| 9 | Bhumare Sandipanrao Asaram · Aurangabad | 87% | 37% | 29 | 57 |
| 10 | Anup Sanjay Dhotre · Akola | 67% | 42% | 41 | 57 |
| 11 | Aashtikar Patil Nagesh Bapurao · Hingoli | 73% | 38% | 38 | 57 |
| 12 | Sanjay Haribhau Jadhav · Parbhani | 55% | 30% | 28 | 57 |
Source: MoSPI eSAKSHI (eSAKSHI API (mplads.mospi.gov.in)). Fund utilisation = works recommended ÷ allocated limit (MoSPI’s definition); spent = vendor payments ÷ allocated limit; completion = completed ÷ recommended works. The MP score weighs completion, spending efficiency, utilisation, proof of work, spending and vendor diversity. How it’s calculated.