40th of 40 from Bihar
Allocated limit
₹28.92 Cr
Median ₹8.60 Cr
Fund utilisation
64%
₹18.45 Cr recommended · 46 works
Below median (98%)
Paid to vendors
₹8.56 Cr
30% of allocation
Below median (88%)
Works completed
18
39% of recommended
Below median (83%)
From recommendation to completion
Every work this MP recommended, by stage
- Recommended by the MP46 works
₹18.45 Cr · 64% of the ₹28.92 Cr allocated
- Sanctioned by the district46 works
100% sanctioned · took 2.4 months on average (due within 45 days)
- Completed18 works
₹3.41 Cr final cost · 16.9 months from recommendation on average
In plain words
What the numbers say
- Recommended 46 works worth ₹18.45 Cr, a fund utilisation of 64%, higher than 2.4% of 17th Lok Sabha MPs.
- The district has sanctioned 46 of them, taking 2.4 months on average.
- ₹8.56 Cr has been paid to vendors, 30% of the allocation.
- 18 works are complete, typically 16.9 months after recommendation. 18 works have geo-tagged photos on eSAKSHI.
- The largest share of funds went to Community buildings & public spaces.
- Payments went to 15 vendors. The largest received 39%.
- No citizen ratings have been reported for completed works.
How the score is made
MP score 55/100: finishing works counts most
- Works completed 30%39Completed ÷ recommended works.
- Spending efficiency 20%40Value of completed works ÷ money paid out. Money paid without works finished scores low.
- Fund utilisation 15%64Value of works recommended ÷ allocated limit (MoSPI’s measure).
- Proof of work 15%100Share of completed works with photos or documents uploaded on eSAKSHI.
- Funds spent 10%30Paid to vendors ÷ allocated limit.
- Vendor diversity 10%77How spread out payments are: full marks when no vendor gets over 20% of the money, none when one vendor gets everything.
i
Members of Parliament (MPs) do not have direct, operational control over the specific vendors selected for government public works. However, they exert significant indirect influence by shaping procurement frameworks, passing supplier diversity laws, and conducting oversight.
Largest vendor: BIOLUNAR ENERGY SOLUTION, 39% of payments across 15 vendors.
District sanction speed
96/100 · sanction is the district authority’s job, so this doesn’t change the MP’s rank
- Sanction speed 100%96Average days to sanction (full marks within the 45-day guideline, none at a year), and the share of works not overdue.
Activity over time
Recommendations, payments and completions by month
Sectors
Value of works by category
Who got paid
Top vendors by payments received
Implementing district authorities
The districts that sanction and execute this MP’s works
Works
46 works · tap “Photos” to see geo-tagged photos from eSAKSHI
Construction of Two Rooms in Kewani High School, Kevani, Garkha
Education & librariesConstruction of rooms and halls in school and colleges· Saran· #86320
₹14.8 L Completed 7 Sept 2026Rec. 21 Jan 2024Paid ₹14.8 LConstruction of two rooms with bathrooms, toilets and handpump in hospital of Rasidpur village of Motirajpur Panchayat in Garkha block.
HealthConstruction of rooms and facilities for hospitals, FWC , PHC Centers and ANM centers· Saran· #106531
₹14.9 L Work partially Completed · 19 Mar 2026Rec. 16 Feb 2024Paid ₹9.1 LConstruction of Community Hall at Gangajal Badkabageecha, Sonepur
Community buildings & public spacesConstruction of community centers and community halls· Saran· #114330
₹6.8 L Completed 23 Feb 2026Rec. 25 Feb 2024Paid ₹6.8 LConstruction of two rooms and toilets for the demolished Ambedkar library in Naharpur village under Naharpur Panchayat
Education & librariesConstruction of public libraries and reading rooms· Saran· #8096
₹14.9 L Completed 11 Feb 2026Rec. 5 Aug 2023Paid ₹14.9 LConstruction of boundary wall on the west side of the main building of Vishwaprabha Community Center, Amanur
Community buildings & public spacesConstruction of boundary walls of existing public and community buildings· Saran· #80224
₹14.8 L Completed 11 Feb 2026Rec. 11 Jan 2024Paid ₹14.8 LConstruction of boundary wall on the east side of the main building of Vishwaprabha Community Center, Amanur
Community buildings & public spacesConstruction of boundary walls of existing public and community buildings· Saran· #80225
₹9.3 L Completed 11 Feb 2026Rec. 11 Jan 2024Paid ₹9.3 LConstruction of Paver Block at Amrit Sarovar, Amnour Pokhara, Saran
Community buildings & public spacesDevelopment of public parks· Saran· #100706
₹13.7 L Completed 20 Jan 2026Rec. 8 Feb 2024Paid ₹13.7 LConstruction of two rooms and toilet in Jawania workshop under Aghara Panchayat
Community buildings & public spacesConstruction of additional rooms and halls in the existing public and community building· Saran· #15526
₹14.9 L Completed 22 Aug 2025Rec. 2 Sep 2023Paid ₹14.9 L????? ????? ???? ????? ?? ?????? ??? ??? ??????? ??? ??? ?? ???????
Community buildings & public spacesDevelopment of public parks· Saran· #8052
₹8.6 L Completed 21 Aug 2025Rec. 4 Aug 2023Paid ₹8.6 LConstruction of Boundary Wall and Entrance Gate of Vishwaprabha Community Center, Amnour
Community buildings & public spacesConstruction of boundary walls of existing public and community buildings· Saran· #8066
₹14.7 L Completed 21 Aug 2025Rec. 4 Aug 2023Paid ₹14.7 LConstruction of Open Gym in Children Park, Chhapra
Sports & fitnessInstallation of fixed garden gym equipment· Saran· #28159
₹17.1 L Completed 27 Feb 2025Rec. 28 Sep 2023Paid ₹17.1 LTO PROVIDE HIGH MAST LIGHT IN NAINI, CHAPRA SADAR, SARAN
Electricity & lightingLighting of public spaces· Saran· #103994
₹8.5 L Completed 5 Dec 2024Rec. 13 Feb 2024Paid ₹8.5 LConstruction of Kids Play Station Center on the right side of the entrance in Children Park, Chapra
Sports & fitnessInstallation of fixed garden gym equipment· Saran· #28154
₹24.9 L Completed 5 Nov 2024Rec. 28 Sep 2023Paid ₹24.9 LConstruction of two rooms at Middle School, Basatpur Bangla
Education & librariesConstruction of rooms and halls in school and colleges· Saran· #12246
₹13.2 L Completed 30 Oct 2024Rec. 22 Aug 2023Paid ₹13.2 LProviding 50 Computers, 50 UPS, 50 Webcam, 50 Printer in Jivika Centre at Chapra, Saran
Education & librariesPurchase of IT systems, including hardware and software for educational purposes· Saran· #101155
₹57.6 L Completed 3 Jun 2024Rec. 9 Feb 2024Paid ₹57.6 L
17th Lok Sabha MPs from Bihar
Ranked by MP score
| # | MP | Utilisation | Spent | Completed | Score |
|---|---|---|---|---|---|
| 1 | Smt Kavita Singh · Siwan | 99% | 99% | 109 | 98 |
| 2 | Ajay Nishad · Muzaffarpur | 97% | 97% | 73 | 98 |
| 3 | Shri Prince Raj · Samastipur | 99% | 99% | 90 | 97 |
| 4 | Mahabali Singh · Karakat | 99% | 99% | 106 | 97 |
| 5 | Alok Kumar Suman · Gopalganj | 100% | 100% | 104 | 97 |
| 6 | Smt Veena Devi · Vaishali | 96% | 96% | 76 | 97 |
| 7 | Kaushalendra Kumar · Nalanda | 85% | 84% | 287 | 96 |
| 8 | Ravi Shankar Prasad · Patna Sahib | 88% | 87% | 198 | 96 |
| 9 | Giriraj Singh · Begusarai | 94% | 93% | 71 | 94 |
| 10 | Shri Janardan Singh Sigriwal · Maharajganj | 93% | 89% | 98 | 94 |
| 11 | Chhedi Paswan · Sasaram | 97% | 97% | 85 | 94 |
| 12 | Chaudhary Mehboob Ali Kaiser · Khagaria | 97% | 96% | 159 | 93 |
Source: MoSPI eSAKSHI (eSAKSHI API (mplads.mospi.gov.in)). Fund utilisation = works recommended ÷ allocated limit (MoSPI’s definition); spent = vendor payments ÷ allocated limit; completion = completed ÷ recommended works. The MP score weighs completion, spending efficiency, utilisation, proof of work, spending and vendor diversity. How it’s calculated.