Works waiting for sanction
66 recommended works are still awaiting sanction more than 45 days later. Sanction is the district authority’s responsibility.
No completed works reported
68 works recommended, none reported complete yet.
Allocated limit
₹14.70 Cr
Median ₹14.70 Cr
Fund utilisation
34%
₹5.01 Cr recommended · 68 works
Below median (76%)
Paid to vendors
₹12.1 L
0.8% of allocation
Below median (37%)
Works completed
0
0% of recommended
Below median (28%)
From recommendation to completion
Every work this MP recommended, by stage
- Recommended by the MP68 works
₹5.01 Cr · 34% of the ₹14.70 Cr allocated
- Sanctioned by the district2 works
2.9% sanctioned · took 53 days on average (due within 45 days)
- Completed0 works
₹0 final cost
66 works are still awaiting sanction, 66 of them for more than 45 days.
In plain words
What the numbers say
- Recommended 68 works worth ₹5.01 Cr, a fund utilisation of 34%, higher than 5.7% of 18th Lok Sabha MPs.
- The district has sanctioned 2 of them, taking 53 days on average.
- ₹12.1 L has been paid to vendors, 0.8% of the allocation.
- 0 works are complete.
- The largest share of funds went to Roads & bridges.
- Payments went to 1 vendors. The largest received 100%.
- No citizen ratings have been reported for completed works.
How the score is made
MP score 6/100: finishing works counts most
- Works completed 30%0Completed ÷ recommended works.
- Spending efficiency 20%0Value of completed works ÷ money paid out. Money paid without works finished scores low.
- Fund utilisation 15%34Value of works recommended ÷ allocated limit (MoSPI’s measure).
- Proof of work 15%0Share of completed works with photos or documents uploaded on eSAKSHI.
- Funds spent 10%1Paid to vendors ÷ allocated limit.
- Vendor diversity 10%Not enough dataHow spread out payments are: full marks when no vendor gets over 20% of the money, none when one vendor gets everything.
i
Members of Parliament (MPs) do not have direct, operational control over the specific vendors selected for government public works. However, they exert significant indirect influence by shaping procurement frameworks, passing supplier diversity laws, and conducting oversight.
Largest vendor: SHARMA CONSTRUCTION, 100% of payments across 1 vendors.
District sanction speed
3/100 · sanction is the district authority’s job, so this doesn’t change the MP’s rank
- Sanction speed 100%3Average days to sanction (full marks within the 45-day guideline, none at a year), and the share of works not overdue.
Activity over time
Recommendations, payments and completions by month
Sectors
Value of works by category
Who got paid
Top vendors by payments received
Implementing district authorities
The districts that sanction and execute this MP’s works
Works
68 works · the 60 most recent are listed here, all of them in the explorer · tap “Photos” to see geo-tagged photos from eSAKSHI
Construction of Community Hall near Shri.Gajanan Maharaj Sansthan at open space Grampanchayat place
Community buildings & public spacesConstruction of community centers and community halls· Buldhana· #306195
₹10.0 L Awaiting sanction · 72 daysRec. 21 Aug 2026Construction of paver blocks and a protective wall on the Gram Panchayat land near the statue of Chhatrapati Shivaji Maharaj at Mauje Chaigaon, Taluka Mehkar.
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Buldhana· #275430
₹7.0 L Awaiting sanction · 200 daysRec. 15 Apr 2026Construction of paver blocks and a protective wall on the Gram Panchayat land near the statue of Chhatrapati Shivaji Maharaj at Mauje Hivra Sable, Taluka Mehkar.
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Buldhana· #275434
₹7.0 L Awaiting sanction · 200 daysRec. 15 Apr 2026Construction of paver blocks and a protective wall on the Gram Panchayat land near the statue of Chhatrapati Shivaji Maharaj at Mauje Lavna, Taluka Mehkar.
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Buldhana· #275436
₹7.0 L Awaiting sanction · 200 daysRec. 15 Apr 2026Construction of paver blocks and a protective wall on the Gram Panchayat land near the statue of Chhatrapati Shivaji Maharaj at Mauje Kambarkhed, Taluka Mehkar.
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Buldhana· #275437
₹7.0 L Awaiting sanction · 200 daysRec. 15 Apr 2026Construction of paver blocks and a protective wall on the Gram Panchayat land near the statue of Chhatrapati Shivaji Maharaj at Mauje Savatra, Taluka Mehkar.
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Buldhana· #275438
₹7.0 L Awaiting sanction · 200 daysRec. 15 Apr 2026Construction of paver blocks and a protective wall on the Gram Panchayat land near the statue of Chhatrapati Shivaji Maharaj at Mauje Mausambewadi, Taluka Mehkar.
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Buldhana· #275439
₹7.0 L Awaiting sanction · 200 daysRec. 15 Apr 2026Construction of paver blocks and a protective wall on the Gram Panchayat land near the statue of Chhatrapati Shivaji Maharaj at Mauje Ukali, Taluka Mehkar
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Buldhana· #275440
₹7.0 L Awaiting sanction · 200 daysRec. 15 Apr 2026Construction of paver blocks and a protective wall on the Gram Panchayat land near the statue of Chhatrapati Shivaji Maharaj at Mauje Sukali, Taluka Mehkar.
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Buldhana· #275443
₹7.0 L Awaiting sanction · 200 daysRec. 15 Apr 2026Construction of paver blocks and a protective wall on the Gram Panchayat land near the statue of Chhatrapati Shivaji Maharaj at Mouje Mohkhed, Taluka Mehkar.
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Buldhana· #275444
₹7.0 L Awaiting sanction · 200 daysRec. 15 Apr 2026Execution of paver block paving, construction of a protective wall, and other ancillary works on the Gram Panchayat land adjacent to the statue of Chhatrapati Shivaji Maharaj at Mauje Anjani Bu., Taluka Mehkar.
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Buldhana· #276410
₹7.0 L Awaiting sanction · 200 daysRec. 15 Apr 2026Execution of paver block paving, construction of a protective wall, and other ancillary works on the Gram Panchayat land adjacent to the statue of Chhatrapati Shivaji Maharaj at Mauje Janefal., Taluka Mehkar.
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Buldhana· #276425
₹7.0 L Awaiting sanction · 200 daysRec. 15 Apr 2026Execution of paver block paving, construction of a protective wall, and other ancillary works on the Gram Panchayat land adjacent to the statue of Chhatrapati Shivaji Maharaj at Mauje Digras BK, Taluka Deulgaon Raja
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Buldhana· #276426
₹7.0 L Awaiting sanction · 200 daysRec. 15 Apr 2026Execution of paver block paving, construction of a protective wall, and other ancillary works on the Gram Panchayat land situated in front of Dr Babasaheb Ambedkars statue at Mouje Gharod, Taluka Khamgaon.
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Buldhana· #276431
₹7.0 L Awaiting sanction · 200 daysRec. 15 Apr 2026Execution of paver block paving, construction of a protective wall, and other ancillary works on the Gram Panchayat land adjacent to the statue of Chhatrapati Shivaji Maharaj at Mauje Dhotra Bhangoji, Taluka Chikhli.
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Buldhana· #276853
₹7.0 L Awaiting sanction · 200 daysRec. 15 Apr 2026
18th Lok Sabha MPs from Maharashtra
Ranked by MP score
| # | MP | Utilisation | Spent | Completed | Score |
|---|---|---|---|---|---|
| 1 | Smita Uday Wagh · Jalgaon | 11% | 9.5% | 9 | 74 |
| 2 | Adv Gowaal Kagada Padavi · Nandurbar | 60% | 22% | 191 | 72 |
| 3 | Chhatrapati Shahu Shahaji · Kolhapur | 100% | 30% | 37 | 67 |
| 4 | Bajrang Manohar Sonwane · Beed | 60% | 26% | 34 | 62 |
| 5 | Nitin Jairam Gadkari · Nagpur | 92% | 29% | 19 | 59 |
| 6 | Bachhav Shobha Dinesh · Dhule | 70% | 14% | 19 | 59 |
| 7 | Ravindra Vasantrao Chavan · Nanded | 85% | 39% | 34 | 58 |
| 8 | Murlidhar Mohol · Pune | 100% | 13% | 12 | 58 |
| 9 | Bhumare Sandipanrao Asaram · Aurangabad | 87% | 37% | 29 | 57 |
| 10 | Anup Sanjay Dhotre · Akola | 67% | 42% | 41 | 57 |
| 11 | Aashtikar Patil Nagesh Bapurao · Hingoli | 73% | 38% | 38 | 57 |
| 12 | Sanjay Haribhau Jadhav · Parbhani | 55% | 30% | 28 | 57 |
Source: MoSPI eSAKSHI (eSAKSHI API (mplads.mospi.gov.in)). Fund utilisation = works recommended ÷ allocated limit (MoSPI’s definition); spent = vendor payments ÷ allocated limit; completion = completed ÷ recommended works. The MP score weighs completion, spending efficiency, utilisation, proof of work, spending and vendor diversity. How it’s calculated.